Hi Ainsley



This one is for the wish list in V 11.



You should contact to Asta Team to get it in the software - same as Lock Dateline to page.



Meanwhile - instead of using page breaks you can turn each print page into a "project".



It is a cumbersome solution but the logic will be unchanged.



Best regards



Mike Testro