Move part completed links - a blooper or magic?

Member for

21 years 8 months

Mike,



I am looking for the very basic PERT view where you communicate logic in a graphic way instead of prose. This is a functionality all software does have. Microplanner had both, activity on arrow (CPM) and activity on node (PDM ) diagrams, even better.



I am having some issues with the updating by percentage as this method I never use, I use remaining duration. What happens to your remaining duration as an activity is updated over several updating periods but with no change in % complete? What is the formula?



A feature to link around complete and / or part completed tasks sounds interesting. The problem is I do not have the manual to help me out figure out these functions and help is not there as in other software where at every screen or dialog box you have a help button that goes directly to where you are, not much of a help. You cannot even click on help without closing the dialog boxes, this is bad, no excuse, not a single bookmark.



I want to call to the attention that Asta Support is unparallel; they answer my questions even for a trial and even follow up. My criticism is in the hope registered users ask for improvements and Powerproject becomes even better.



Best regards,

Rafael

Member for

19 years 10 months

Hi Rafael



Powerproject has a feature to link around complete and / or part completed tasks.



So even if you have a lead lag link where progress goes beyong the link the logic will re link itself after re-schedule.



Best regards



Mike Testro

Member for

21 years 8 months

Another way to look for out-of-sequence is through the PERT view and Trace Logic Views available in most CPM software. You would see crossed out boxes for finished activities and visually can very easy pinpoint out-of-sequence.



Where Powerproject does provides for this very basic functionality?



Best regards,

Rafael

Member for

21 years 8 months

Thanks Mike.



If I were into house building I would give you 10ea P3 licenses for a single Powerproject license, here it shines.



Best regards,

Rafael

Member for

19 years 10 months

Hi Rafael



I am only a simple delay analyst who uses about 20% of PowerProject facilities so your query:



"I still want your answer about whether omitting from the out-of-sequence report these activities is a good idea."



Leaves me quaking in my boots - I honestly have no idea.



I will get in touch with the CEO of Asta to see if he can make direct contact with you.



You could be of real mutual help to each other.



Best regards



Mike Testro.

Member for

21 years 8 months

Mike,



Yes lead and lags is precisely where you will find most of your out-of-sequence. With bottom-up you do not have lags so it will happen elsewhere unless you are fooling the system by setting 100% complete to some of your bottom-up activities you assigned an “arbitrary duration” as arbitrary as lag. Even with only FS relationships and no lag you might get into out-of-sequence, just a change in course, “sh..t” happens.



Bottom-up after the fact, isn’t it what Powerproject pretend to do as if the answer for all out-of-sequence issues? Primavera and Microsoft guys missed it; guess you will call them rubbish.



I still want your answer about whether omitting from the out-of-sequence report these activities is a good idea.



Best regards,

Rafael

Member for

19 years 10 months

Hi Rafael



I use this facility when adding progress to charts that have lead lag links.



It is not necessary when using a true bottom up programme with only FS links.



You are really getting into this.



I think you should contact Richard Ormerod at Asta and ask if you can be part of the Beta testing group for V 11 or 12.



Best regards



Mike Testro