Filtering on Predecessors and Successors

Member for

16 years 5 months

When inside this P&S view, what’s the quickest way to jump to the pred/suc of one of those activities in the view?

Member for

24 years 2 months

Oliver



From an unfiltered view, click on the activity whose predecessors / successors you wish to see.



Then go to toolbar, select view. From the drop down menu select view and from the next drop doown menu you should see an option for Predecessors & Successors. Click this and this gives you your direct predecessors and successors



Knowing (or not as the case maybe) PowerProject, there is probably a shortcut to do the above!



Hope this helps



Mal