Asta Powerproject Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2007-12-12 10:52 Permalink RE: Copying Dates into Start and End Fields Peter, I tried as follows, and it woks so so: a) enter the desired dates in the custom field, b) select all the cells in the column by dragging the mouse; do not rigt click on the column header to click Copy, does not work, c) select the same number of rows in the Start column, and click Paste. It works, except for milestones, multi-task bars. Hope it helps, Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2007-12-12 10:52 Permalink RE: Copying Dates into Start and End Fields Peter, I tried as follows, and it woks so so: a) enter the desired dates in the custom field, b) select all the cells in the column by dragging the mouse; do not rigt click on the column header to click Copy, does not work, c) select the same number of rows in the Start column, and click Paste. It works, except for milestones, multi-task bars. Hope it helps, Alexandre
Member for
22 years 9 monthsRE: Copying Dates into Start and End Fields
Peter,
I tried as follows, and it woks so so:
a) enter the desired dates in the custom field,
b) select all the cells in the column by dragging the mouse; do not rigt click on the column header to click Copy, does not work,
c) select the same number of rows in the Start column, and click Paste.
It works, except for milestones, multi-task bars.
Hope it helps,
Alexandre