Asta Powerproject Member for 19 years Member for 19 years Submitted by Laurie Willis on Wed, 2007-11-21 05:44 Permalink RE: Formatting the weekend display Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didnt have a chance to try out your suggestion. But thank you for your help. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2007-11-06 13:38 Permalink RE: Formatting the weekend display Laurie, I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Week-end: 08:00 (or 09:00) - 17:00 Non-working: 17:00 - 00:00 and as follows in the 8hr/day, 7d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Working: 08:00 (or 09:00) - 12:00 Non-working: 12:00 - 13:00 Working: 13:00 - 17:00 Non-working: 17:00 - 00:00 I presume the wrong display comes from there. Hope this helps Alexandre Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Laurie Willis on Wed, 2007-11-21 05:44 Permalink RE: Formatting the weekend display Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didnt have a chance to try out your suggestion. But thank you for your help.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2007-11-06 13:38 Permalink RE: Formatting the weekend display Laurie, I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Week-end: 08:00 (or 09:00) - 17:00 Non-working: 17:00 - 00:00 and as follows in the 8hr/day, 7d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Working: 08:00 (or 09:00) - 12:00 Non-working: 12:00 - 13:00 Working: 13:00 - 17:00 Non-working: 17:00 - 00:00 I presume the wrong display comes from there. Hope this helps Alexandre
Member for
19 yearsRE: Formatting the weekend display
Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didnt have a chance to try out your suggestion.
But thank you for your help.
Member for
22 years 9 monthsRE: Formatting the weekend display
Laurie,
I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern:
Non-working: 00:00 - 09:00 (or 08:00)
Week-end: 08:00 (or 09:00) - 17:00
Non-working: 17:00 - 00:00
and as follows in the 8hr/day, 7d/w pattern:
Non-working: 00:00 - 09:00 (or 08:00)
Working: 08:00 (or 09:00) - 12:00
Non-working: 12:00 - 13:00
Working: 13:00 - 17:00
Non-working: 17:00 - 00:00
I presume the wrong display comes from there.
Hope this helps
Alexandre