Current view progress only calculated and not hidden

Member for

19 years 10 months

Hi Bernie



Welcome to Planning Planet



You can enter progress on a filtered view on all or selected tasks and it will be effective when you drop the filter.



Make sure you tick the Link Around Completed Tasks when doing the excercise.



Best regards



Mike Testro