Another, maybe quicker way to check what calendar has been assigned is to add a column to the spreadsheet table and make it display token>date>calendar. This works fine unless you have more than one calender assigned to the tasks on the bar line.
Good luck!
Jamie
Member for
19 years
Member for19 years
Submitted by Laurie Willis on Fri, 2006-11-24 05:33
Right click on the task bar to open the Properties dialog, select the Task tab, read the Calendar field; use this field to possibly select another calendar.
Member for
23 years 7 monthsRE: Checking the Calendar against tasks
Another, maybe quicker way to check what calendar has been assigned is to add a column to the spreadsheet table and make it display token>date>calendar. This works fine unless you have more than one calender assigned to the tasks on the bar line.
Good luck!
Jamie
Member for
19 yearsRE: Checking the Calendar against tasks
Got it. Thanks Alexandre.
Member for
22 years 9 monthsRE: Checking the Calendar against tasks
Laurie,
Right click on the task bar to open the Properties dialog, select the Task tab, read the Calendar field; use this field to possibly select another calendar.
All the best,
Alexandre