Did you have any joy using Asta? The new update looks a bit well.. complicated. I have set up an excel based S-Curve, which providing you use Unique ID and Vlookups it will generate a more company friendly presentation. It is a large file if you have any suggestions where to post for download, I would be happy to send.
Rgds
Robbin
Member for
21 years 1 month
Member for21 years2 months
Submitted by Stephen Magill on Tue, 2008-08-12 04:53
do you want the original asta instructions? i dont know if they are still available from the asta website. i have them here as a pdf if you want.
Speaking to asta about the s-curve macro, they said the new version is about to be released so hopefully it will have a new set of instructions and be a touch more user friendly.
Theres also a much needed bit of information regarding the .pet and .bak files that if ur having problems with s-curves, may help. if you need me to explain, let me know.
Member for
17 years 7 months
Member for17 years8 months
Submitted by Karen Pender on Mon, 2008-08-11 13:37
If anyone else has it, could they forward it on? I dont think stewart has been in in a while. i tried emailing him directly but still havnt got a response.
ive went back to the asta instructions which are, to be fair, absolute nonsense.
Member for
19 years 10 months
Member for19 years10 months
Submitted by Cherie S Blare on Tue, 2008-04-01 12:53
i know it was a wee while ago you posted but hopefully you still have that step by step guide. asta have taken the link down allowing you to download the presentations and the course i went to provided me with a booklet but i left it with my old company when i changed jobs. could you send a copy to s.magill@pelliott.com?
would be much appreciated, i too have the problem of forgeting how to do it from project to project
cheers
stephen
Member for
23 years 7 months
Member for23 years7 months
Submitted by David Bordoli on Wed, 2006-11-29 11:09
At the recent AstaPowerproject National User Forum (22 December, Richard Ormerod gave a presentation: Managing Progress and S Curves in Asta Powerproject.
Member for
16 years 7 monthsAll, If you want the file
All,
If you want the file from Stewart please send him a private message with your email address, rather than posting here.
Thread locked.
Member for
16 years 7 monthsStewart, I am now using Asta
Stewart,
I am now using Asta Power Project recently and could you please send me a copy as well?
My email address - riyas68@yahoo.com
Regards,
Riyas
Member for
15 years 6 monthsHi Stewart, It wouls be
Hi Stewart,
It wouls be really helpful if you could email me a copy please. my e mail is smartin@ses-ltd.co.uk.thanks
Member for
14 years 9 monthsStewart, Can you please send
Stewart,
Can you please send me a copy...my email is hoban.rory@gmail.com
what system are you using?
thanks
Member for
14 years 8 monthsDear,Plz send me the copy to
Dear,
Plz send me the copy to engrrana.imran@gmail.com
Regards,
Imran Rana
Member for
18 years 8 monthsHi Stewart, Can you e-mail me
Hi Stewart,
Can you e-mail me instruction-sheet / memory-jogger for the setting up and maintaining of the weekly progress S-curves.
richurose@gmail.com
Regards,
Richu
Member for
17 years 6 monthshi stewart,I would like to
hi stewart,
I would like to have a copy too.. kindly send to mazura_brennan@yahoo.com
Thanks in advance:-)
Member for
14 years 10 monthsCan I pl have a copy of
Can I pl have a copy of REFERENCE PLANNING FOR EPC PIPELINE PROJECTS in primavera P6 on E-mail hu54al@yahoo.co.uk
Member for
14 years 10 monthsStewart,Can you please send
Stewart,
Can you please send me a copy...my email is nanding882008@yahoo.com.
Thanks,
Nanding
Member for
15 yearsI would like a copy please
I would like a copy please mate.
My email is amocke@prater.co.uk
Cheers
Member for
15 years 4 monthsHi I would like a
Hi
I would like a copy.
please forward to hdhansay@gmail.com
Thanks
Member for
19 years 11 monthsi would appreciate a copy
i would appreciate a copy please: khaleel195@yahoo.com
Member for
15 years 5 monthshi Stewart,I’d like a copy if
hi Stewart,
I’d like a copy if possible , EMAIL at steve.ogley@mccabeuk.co.uk
thanks in advance
Member for
19 years 10 monthsHi All Setting up S curves is
Hi All
Setting up S curves is just one module in Planning Academy tuition set Advanced Planning for Builders
Visit
www.planning-academy.co.uk
to discover more.
Best regards
Mike Testro
Member for
14 years 11 monthsMay I have a copy please,
May I have a copy please, mehmet.erkam@yahoo.com
Thanks in advance!
Member for
19 yearsRE: How to set up+update the weekly progress S-curves
Would like a copy, please send to cadams@australand.com.au
Cheers!
Member for
19 years 10 monthsRE: How to set up+update the weekly progress S-curves
Pls send me a copy too..
Member for
16 years 9 monthsRE: How to set up+update the weekly progress S-curves
can you send it to me as we to greatfargo@yahoo.com
Member for
18 years 4 monthsRE: How to set up+update the weekly progress S-curves
Hi Everybody,
I am new in this group & would like to have copy of the same.
Those who have these steps, pls mail to the following address ak_sumaiya@yahoo.co.in
Regards
Nokhez
Member for
21 years 1 monthRE: How to set up+update the weekly progress S-curves
dunno if you were talking about robins stuff or my stuff bonnie but ive sent you progress expert 2 and the instruction pdf as well.
any bother feel free to email me.
Cheers
Stephen
Member for
16 years 8 monthsRE: How to set up+update the weekly progress S-curves
I could really use this too. Can you email it to me at brimont2@mvdsl.com
Thanks
Bonnie
Member for
21 years 1 monthRE: How to set up+update the weekly progress S-curves
Krishnan,
all the stuff should be on its way to you.
Robbin,
sorry i didnt get notification of ur last post. what size is the file when zipped?
i would really appreciate it.
Regards
Stephen
Member for
16 years 10 monthsRE: How to set up+update the weekly progress S-curves
Hi All
Recently joined the group. Even being an old thread, would like to have a copy of the same.
Those who have these steps, pls mail to the following address krishnan_uae@yahoo.com
Regards
RK
Member for
22 years 2 monthsRE: How to set up+update the weekly progress S-curves
Hi Stephen,
Did you have any joy using Asta? The new update looks a bit well.. complicated. I have set up an excel based S-Curve, which providing you use Unique ID and Vlookups it will generate a more company friendly presentation. It is a large file if you have any suggestions where to post for download, I would be happy to send.
Rgds
Robbin
Member for
21 years 1 monthRE: How to set up+update the weekly progress S-curves
do you want the original asta instructions? i dont know if they are still available from the asta website. i have them here as a pdf if you want.
Speaking to asta about the s-curve macro, they said the new version is about to be released so hopefully it will have a new set of instructions and be a touch more user friendly.
Theres also a much needed bit of information regarding the .pet and .bak files that if ur having problems with s-curves, may help. if you need me to explain, let me know.
Member for
17 years 7 monthsRE: How to set up+update the weekly progress S-curves
Hi guys did anyone get the instructions for setting up S- Curves?
Could I get a copy please?
karenpender@gmail.com
Member for
17 years 7 monthsRE: How to set up+update the weekly progress S-curves
Hi,
Please send me copy of weekly "S" curve.
salah.ahmed80@yahoo.ca
Thanks
Salah
Member for
21 years 1 monthRE: How to set up+update the weekly progress S-curves
If anyone else has it, could they forward it on? I dont think stewart has been in in a while. i tried emailing him directly but still havnt got a response.
ive went back to the asta instructions which are, to be fair, absolute nonsense.
Member for
19 years 10 monthsRE: How to set up+update the weekly progress S-curves
Hi
Can you send a copy to lisacatedwards@yahoo.co.uk
Thanx
Member for
18 years 2 monthsRE: How to set up+update the weekly progress S-curves
Id be grateful if you can send me a copy at eva.bristow@brookfieldeurope.com.
Thanks a lot,
Eva
Member for
17 years 7 monthsRE: How to set up+update the weekly progress S-curves
hi can i get the weekly progress of s-curves.whoever got it please send it to me on tumharabina@yahoo.com
Member for
21 years 1 monthRE: How to set up+update the weekly progress S-curves
Hi Stuart,
i know it was a wee while ago you posted but hopefully you still have that step by step guide. asta have taken the link down allowing you to download the presentations and the course i went to provided me with a booklet but i left it with my old company when i changed jobs. could you send a copy to s.magill@pelliott.com?
would be much appreciated, i too have the problem of forgeting how to do it from project to project
cheers
stephen
Member for
23 years 7 monthsRE: How to set up+update the weekly progress S-curves
Hi Mike
I just went to Astas web site http://www.astadev.com
then chose News & events from the top menu and on the right-hand side, half way up/down the page is a link to PRESENTATION DOWNLOADS.
Good luck
David
Member for
19 years 3 monthsRE: How to set up+update the weekly progress S-curves
Hello Mike - please sned me your email address so I can attach the sheets
Cheers
Stewart
Member for
20 years 6 monthsRE: How to set up+update the weekly progress S-curves
I would like to see this as I attended the forum late and missed this particualr talk
however cant seem to link to this
and cant see access to it on astas web site
can you help
Member for
23 years 7 monthsRE: How to set up+update the weekly progress S-curves
Sorry about the dumb formatting, the second link should be:
S-Curves
Member for
23 years 7 monthsRE: How to set up+update the weekly progress S-curves
Hi all
At the recent AstaPowerproject National User Forum (22 December, Richard Ormerod gave a presentation: Managing Progress and S Curves in Asta Powerproject.
Details of most of the presentations are on-line at Forum Details and Richards slides are at http://www.astadev.com/news/events/nuf06/presos/ManagingProgress_S-curv…>S-Curves. You can also down load an example (see the first link).
Regards
David
Member for
19 yearsRE: How to set up+update the weekly progress S-curves
ei guys. itll be much appreciated if youll send me a copy as well. thanx in advance. dekryptor@bluebottle.com.
Member for
19 years 1 monthRE: How to set up+update the weekly progress S-curves
rubenquintaljr@yahoo.com
tnx
Member for
20 years 6 monthsRE: How to set up+update the weekly progress S-curves
Stewart
I would be grateful if you would send me a copy
I will send an e-mail to the address you have given
Many thanks
Mike
Member for
19 years 3 monthsRE: How to set up+update the weekly progress S-curves
Hello Alan
Please could you email me at greens@laingorourke.com and I can send direct to your address as an attachment
Cheers
Stewart