ODBC Export

Member for

20 years 9 months

Brian

I recently had an initial problem similar to this with exporting reports to excel files, you problem may be similar.

With the ASTA support people , we discovered the target file locations were blank and the salient report styles template [needed to run the process] was not being found. The solution was to go to Tools, Options, File locations and modify the file locations to look in the right place.



eg Tabular Report Styles Path = c:programme filesAstaAsta power projectTabReportStyles

similarly HTML is as above plus HTMLstyles

hope it helps.

JK