Project Metro Kaohsiung, Taiwan
Developed Programme/Schedule:
E&M Systems Works Programme (Master Schedule, Primavera P3)
E&M Systems Installation Programme for Contractors reference on DWS Development
Coordination Installation Programme (CIP with Civil, Excel)
Track Related Installation Programme (TRIP with Trackwork Contractor, Excel)
Test and Commissioning Programme (Systems T&C / Interface / Systems Integration, Primavera)
Detailed Systems Integration Test Schedule (Hourly Basis, Excel)
Reporting:
Critical Path Analysis
Update the developed Programme/Schedule
Monthly Progress Report
Bi-Weekly Site Report (Installation Phase)
Claim Management:
Assist Contract Manager on events recording (Risk Management)
Schedule Forecast and Programme Analysis
Developed Programme/Schedule:
E&M Systems Works Programme (Master Schedule, Primavera P3)
E&M Systems Installation Programme for Contractors reference on DWS Development
Coordination Installation Programme (CIP with Civil, Excel)
Track Related Installation Programme (TRIP with Trackwork Contractor, Excel)
Test and Commissioning Programme (Systems T&C / Interface / Systems Integration, Primavera)
Detailed Systems Integration Test Schedule (Hourly Basis, Excel)
Reporting:
Critical Path Analysis
Update the developed Programme/Schedule
Monthly Progress Report
Bi-Weekly Site Report (Installation Phase)
Claim Management:
Assist Contract Manager on events recording (Risk Management)
Schedule Forecast and Programme Analysis