Job Description:
A. Project planning, scheduling, control and monitoring involved in various projects such as:
A.1. M-IO Builders Qatar W.L.L.
Doha, Qatar
- Al Bidda Platinum Tower
2,300 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.
- Al Hitmi Office Building
1,700 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.
- Dubai Tower (Tender Document Preparation)
10,000 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.
A.2. M-IO Builders L.L.C.
Dubai, UAE
- Dubai Metro Project
10 Nos. Metro Rail Stations, 7,700 MT Structural Steel Fabrication and Erection
• Preparation of manpower and equipment histogram.
• Preparation of look-ahead schedules.
• Preparation of project KPI and S-curves.
• Preparation of work orders for site activities.
• Preparation of weekly and monthly progress reports.
• Compilation of progress photos.
B. Over-all logistics supervision and management.
C. M.I.S. (Management Information System)
a. Database programming and management.
D. Pre-award:
a. Project estimate & tender document preparation.
b. Preparation of project schedule.
c. Preparation of manpower & equipment histogram.
E. Quantity Surveying:
a. Review of project BOQ.
b. Assisted in the preparation of progress claims.
c. Compilation and review of FCR (Fabrication Control Report)
d. Compilation and review of ECR (Erection Control Report)
Project Planning, Scheduling, Control and Monitoring involved in various projects., M-IO Builders Sdn Bhd, Al Bidda Platinum Tower; Al Hitmi Office Building; Dubai Metro Stations
START Date