Senior Project Controls Specialist, Fluor Daniel SA, QMM Ilmenite Mine for Rio Tinto (Fort Dauphin, Madagascar)

START Date
END Date

First based in the Home Office Projects Control environment in Johannesburg, where I developed and maintained the Master Project Schedule, during the engineering & procurement phase of the project.

My responsibilities involved co-ordination with engineering and procurement departments to manage the drawing and equipment delivery interfaces with the schedule.

During the construction phase, I was site based in Madagascar, where I was also the ‘Milemarker’ practitioner (a Fluor system for measuring progress and performance).

Planner

11 kV overhead line and early works for Cobalt and nickel extraction plant near Toamasina Madagascar
est cost $13 000 000
6.6 kv overhead line and early works for Cobalt and Nickel mine near Moramanga Madagascar
est cost $ 3 000 000
Nickel and cobalt extraction plant E&I installation to start March 2009
Est cost $ 15 000 000

Planning and scheduling, estimation and costing of extra work.