Critical Path DRAG
Critical Path DRAG (Devaux's Removed Activity Gauge) is the amount of time that an activity on the critical path (i.e., the longest path through the project) is adding to the project’s duration or, alternatively, the amount of time by which the project completion would be pulled in by reducing a critical path activity’s duration to zero.