Delay Event - Calendar Day or Working Days

Member for

16 years 11 months

Many thanks to all

 

Cheer's

Shahul

Member for

19 years 10 months

Hi Shahul

It is important to differentiate the difference between calendar and working days wjen describing cause and effect of a delay event.

The duration of a delay event could be either a working or calendar day duration depending on the nature of the event.

If it is a delay arising from a late preceding activity that is already on the programme then it should be the same calendar as the delaying task.

If it is a late delivery of materials that is not on the programme then a 7 day week calendar would be more appropriate.

The delay effect is always expressed in calendar days.

Best regards

Mike Testro

Member for

16 years 7 months

Shahul,

 

can't you just adjust all your labour calendars to have Friday off, re-run your schedule, and this will tell you your EOT claim?