You have to take into your consederation that the contract documents are complementary and if any requirements mentioned in any part (BOQ, Drawings,Specification,tender clarification,conditon of contract,letter of acceptance.........etc ),it shoud be consedared as part of the original scope of work and not a variation.
Member for
18 years 4 months
Member for18 years4 months
Submitted by Nicolas Igersheim on Thu, 2007-08-09 11:00
Member for
19 years 2 monthsRE: Variation Order
You have to take into your consederation that the contract documents are complementary and if any requirements mentioned in any part (BOQ, Drawings,Specification,tender clarification,conditon of contract,letter of acceptance.........etc ),it shoud be consedared as part of the original scope of work and not a variation.
Member for
18 years 4 monthsRE: Variation Order
hi all
IMHO
Indeed first issue is type of contract:
A)If lump sum:
that sum is supposed to cover all items and/or works shown on contract drawings:
1) an item/work shown requires no extra order
2) an item/work missing does
B)If remeasurable:
the BOQ is supposed to add up all items and/or works shown on as-built drawings,
1) if not: -> remeasure,
2) if drawings are missing, they should be established and measured or at least estimated
in B case, an ambiguity may arise since you use once the word item
and then the word works.
A steel structure BOQ will measure steel frame weights for instance:
one could thus argue the "item" bolts is missing, but it is usually
paid for by the $ rate per ton of steel => no extra order.
Hope I kept it simple and short enough
Regards
Member for
20 years 3 monthsRE: Variation Order
Hi Bensiger,
First what type of contract: Remeasureable or fixed lump sum?
In general
Item 1. First you have to qualify with Client if such missing items will be constructed.
If client confirm yes, then, it is a variation.
Item 2. Also qualify with client the drawings. Checked if the BOQ covers the magnitude of works. write to client your position or idea
In general, the above are variation: could be positive variation or negative variation. The rule of thumb is to clear with client.
Cheers
Joseph