HOW VARIATIONS CAN BE CLAIMED?

Member for

22 years 7 months

Hi Skan,



Sure, all are important factors to be considered as you have mentioned. If you don’t have contract(where some info will be available related to BOQ/measurements etc., clauses related to variations)then how do we define something about variation, only by mutual understanding/agreement we can proceed further.

Member for

19 years 5 months

Hi,



Before we proceed to claiming vairiation, I think:



1) Is there a contractual relationship?

2) What type of contract?

3) What did the contract say?

4) Follow what had been stated in the contract documents

5) If none mentioned, Which standard it is following, JCT? Fidic? NEC? Or home grown?



Will this be the basis to start with?



By the time we reach this stage, if still unclear then we need to agree on the principle to move forward.



I hope my analysis make sense.

Member for

22 years 4 months

Basis of Variations are as under:



a) Upon Written Instructions from Engineers/Consultant



b) Upon Verbal instructions from Engineer but notifying them at the time of occurrence of these events



Wherafter these varaitions can be submitted with fully supporting documents and associated costs therewith. These cots are usually taken as difference from the original BOQ or on new rates whichever mutually agree by both parties or as per Contract

Member for

22 years 7 months

usually variations can be claimed by having well supporting documents/evidence. so always instructions from engineers or architects are highly required to vary anywork. without such a written piece of info, it will be a tough call. may be we can look for reverse confirmation on verbal instructions received from engineer/consultant. just by writing a letter about his verbal instruction pursuant to contracts clause??? ...........