ITEMS REMOVED FROM BOQ

Member for

20 years 10 months

Francis,



Depends on what was in the ammendment to the signed contract. If the ammendment reflected the change in the scope of works then the ammendment may constitute an agreed variation to the original contract made at the time of the letter of acceptance. In this case you may be able to recover something.



OR



The signed contract and ammendment are a completely new contract replacing the original contract. In this case you are unlikely to recover anything.




Member for

18 years 11 months

Hi Mr. Karim. Thanks for reply but where to include then the following:



1. LOA

2. LOI

3. BOQ

4. Drawings

5. Specs

6. Addendum

7. Soil Investigation Report



Thanks again.

Member for

19 years 7 months

a)Contract Agreement:

The signed contract between the employer & the contractor (includes the general & particular conditions and also any annexed memoranda).



b)Particular Conditions:

The particular clauses which is written especially for the contract.



c)General Conditions:

The general clauses according to the FIDIC.



d)Employer’s Requirements:

Means the document entitled employer’s requirements, as included in the Contract, and any additions and modifications to such document in accordance with the Contract. Such document specifies the purpose, scope, and/or design and/or other technical criteria, for the Works.

Can be in the form of letters, material or drawing submittal , etc..



e)Tender and any other documents forming part of the Contract:

means the Contractor’s signed offer for the Works and all other documents which the Contractor submitted therewith.



Regards.

Member for

18 years 11 months

Can someone tell me the particular document/s covered or included in each item below?

a) the Contract Agreement,

(b) the Particular Conditions,

(c) these General Conditions,

(d) the Employer’s Requirements,

(e) the Tender and any other documents forming part of the Contract.

Thanks a lot.

Member for

19 years 7 months

According to the conditions of Fidic for EPC / Turnkey projects the 1st edition in 1999:

The documents forming the Contract are to be taken as mutually explanatory of one another. For the purposes of interpretation, the priority of the documents shall be in

accordance with the following sequence:

(a) the Contract Agreement,

(b) the Particular Conditions,

(c) these General Conditions,

(d) the Employer’s Requirements,

(e) the Tender and any other documents forming part of the Contract.

Member for

22 years 7 months

should your contract follows FIDIC - Conditions of Contract for Works of Civil Engineering Construction, Fourth Edition 1987 Reprinted 1992 with further amendments, you can look for a clause 52.3 Variations Exeeding 15 percent(also check for the conditions of particular application for any changes in the 15%, sometimes they mention 25%). If it is the case you can claim but as you have mentioned some items already been removed from the original scope before signing the agreement. LOA is different story. You are being aware of the changes at the thime of signing the contract, in that case you could have raised this issue. after signing the contract there is no point of talking, only to concentrate on work.



you can look for any clauses available in your contract to account for the above mentioned situation, if it is not mentioned, then no use, only we have to work and finish the project on time.