Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Stonework Floors

 

Sequence of operations...
  •  Expose base slab aggregate, clean, wet slab, apply bonding agent, lay screed topping (50 mm) compact and cure screed.  Once cured, setout lines and levels and lay and tamp stones onto setting bed.  Protect area until cured and maintain protection to prevent traffic damage etc.
  •  Each area should then be grouted after the installation of the paving.  Typical floor block panel size 0.5 m2/stone.

 

Stone floors 10.45 m2/day
Stone staircase tread/risers 8.40 m2/day

 

.    A paving team consists of 1 fixer and 0.5 mate's (1 mate per 2 fixers).

Market Place

No results found... (try selecting a different content filter)