Formwork & Falsework - Ground Foundation Formwork
FORMWORK & FALSEWORK
Ground Foundation Formwork All formwork rates in m2/hr.
Item | Shutter size | Fix | Strike |
To Pilecaps | 0.75 m2 | 1.64 | 3.85 |
0.75 - 1.50 m2 | 1.82 | 4.55 | |
1.50 - 2.25 m2 | 2.00 | 5.00 | |
2.25 - 3.00 m2 | 2.22 | 5.56 | |
exc 3.00 m2 | 2.50 | 7.14 | |
To Foundations | 0.75 m2 | 1.72 | 4.55 |
0.75 - 1.50 m2 | 1.82 | 4.55 | |
1.50 - 3.00 m2 | 2.50 | 6.25 | |
3.00 - 5.00 m2 | 2.63 | 6.67 | |
To Ground Beams | 1.50 m2 | 1.82 | 4.55 |
1.50 - 3.00 m2 | 2.63 | 6.67 | |
3.00 - 5.00 m2 | 2.70 | 7.14 |