Fixing Steel At Ground Level
Rate includes for sorting, transporting, markup, assemble, tie in and block out. Rates in hrs/Tonne (1,000 kg).
Dia Of Steel | Slabs/Fnds | Walls | Stairs | Beams/Cols |
6 mm | 37.9 | 40.2 | 47.4 | 52.2 |
8 mm | 26.4 | 28.2 | 33.0 | 36.3 |
10 mm | 20.2 | 21.6 | 25.2 | 27.7 |
12 mm | 15.8 | 16.8 | 19.8 | 21.8 |
16 mm | 11.0 | 11.7 | 13.8 | 15.2 |
20 mm | 8.2 | 8.7 | 10.2 | 11.2 |
25 mm | 6.2 | 6.7 | 7.8 | 8.6 |
32 mm | 5.3 | 5.6 | 6.9 | 7.2 |
40 mm | 4.4 | 5.6 | 4.2 | 4.6 |
50 mm | 4.1 | 4.5 | - | - |
Comments
Fixing steel crew size
PP Admin,
These rates are extremely useful I am, however, unsure of the crew size required to achieve the rates above.
thanks,
FT