Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

EPC Lead Planner

EPC Lead Planner, James Fisher Nuclear Limited, SGHWR

START Date: 
September, 2020

Lead Planner - James Fisher Nuclear Ltd

  • Took the lead for a number of programmes related to the delivery of a project to deconstruct one of the legacy R&D Reactors for Magnox
  • Developed, with information I collated, a detailed construction programme that included a complicated Mechanical and Electrical installation phase.
  • Rebaselined the contract programme with the civils and M&E installation sequence including the dependencies of the Safety Case Logic required ahead of major construction.
  • Instigated a tracking system for the remaining design deli
Experience Hours (Planning & Scheduling): 
2050
Experience Hours (Cost Management): 
1100
Experience Hours (Forensic Analysis): 
200

EPC Lead Planner, Jacobs CES, BP Khazzan

START Date: 
May, 2014
END Date: 
December, 2016

Produce and issue programme reports in agreed time frame.

Resposible for weekly progress update of the projects.

Experience Hours (Planning & Scheduling): 
5150
Experience Hours (Cost Management): 
5150
Experience Hours (Forensic Analysis): 
5150

EPC Lead Planner, PT. Raga Perkasa Ekaguna, EPCC South Sembakung Gas Plant

START Date: 
July, 2010
END Date: 
June, 2011

• Planning, scheduling and updating Master Schedule (Level 1 – 2) and detail schedule (Level 3 - 4).
• Review, monitoring and preparing project schedule report summaries (including Engineering Document Register, Procurement Schedule, Expediting Report, S-Curve and Progress & Invoice Monthly Report) of Master Schedule that have been assigned.
• Coordinate with Engineering team for monitoring the Engineering deliverable.
• Coordinate with Procurement and Logistic team to monitor material preparation before construction works.

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Forensic Analysis): 
3500

EPC Lead Planner, LUKOIL OVERSEAS SERVICE BV (DUBAI BRANCH), West Qurna II

START Date: 
November, 2014
END Date: 
December, 2015

West Qurna II, Mishrif Full Field Project, Iraq. 

Ø  Develop and maintain Level 2 Project schedules based on the provided scenarios based on the approved WBS

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
450

EPC Lead Planner, AREVA NP, EPR flammanville

START Date: 
November, 2005
END Date: 
December, 2011

Senior Schedule Manager

EPC Lead Planner, PREMIER OIL, Solan

START Date: 
March, 2014
END Date: 
September, 2014
Solan project. Construction of the jacket and the topside at the Bifab yard. Managed the Jacket construction planning scope • Provided new detailed estimation tools of the Load-out planned date, using production daily results (bracers and infills installed/welded out). • Optimized the schedule of the Rigging contractor and its interactions with production. Directed a team of 2 production planners • Trained the team to become proficient with Primavera P6. • Supported production team by identifying daily priorities and critical path. • Delivered daily production reports.

EPC Lead Planner, SNC Lavalin, Western Alberta Tranmission Line $1.5B

START Date: 
December, 2011
Over 18 years of experience in Project Controls in Power, Oil and Gas & Industrial sectors.Knowledgeable and experienced in all aspects of Planning and Controls includingforecasting, man-hour control, risk analysis, Earned Value, Progress Measurement, quality control, and report preparation .Expertise in Project/Program Schedule Diagnostics, forensics analysis and benchmarking .Able to perform/generate Estimates, Cost andSchedule Validation and Risk Analysis .Expert in critical path method (CPM) analysis,variance analysis, float analysis and schedule trending and KPIs like CPI & SPI .Compute
Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
15500
Experience Hours (Forensic Analysis): 
1000

EPC Lead Planner, Jacobs, Mining projects

START Date: 
October, 2010
Develop Detailed Schedule Baseline for Engineering and Procurement Services Reporting weekly, monthly and update the schedule Identify constrains, delays, evaluation of impact, forecasting on the baseline schedule Monthly update of EPCM schedule, coordination of interactive planning session Mentor of other co works and coordinate the calculate of progress of all project Evaluate progress of subcontractor of structural steel erection, mechanical erection and piping. Evaluate the acceleration schedule to comply the client’s requirements. Perform 3 week look ahead, 90 days look ahead.
Experience Hours (Planning & Scheduling): 
11000
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

EPC Lead Planner, Jacobs, Mining projects

START Date: 
October, 2010
Develop Detailed Schedule Baseline for Engineering and Procurement Services Reporting weekly, monthly and update the schedule Identify constrains, delays, evaluation of impact, forecasting on the baseline schedule.

.  Monthly update of EPCM schedule, coordination of interactive planning session

. Mentor of other co works and coordinate the calculate of progress of all project

Experience Hours (Planning & Scheduling): 
11000
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

EPC Lead Planner, Jacobs, Mining projects

START Date: 
October, 2010

.  Develop Detailed Schedule Baseline for Engineering & Procurement Services

.  Reporting weekly, monthly and update the schedule.

.  Identify constrains, delays, evaluation of impact, forecasting on the baseline schedule.

.  Monthly update of EPCM schedule, coordination of interactive planning session

Experience Hours (Planning & Scheduling): 
11000
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Market Place