Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Solan

EPC Lead Planner, PREMIER OIL, Solan

START Date: 
March, 2014
END Date: 
September, 2014
Solan project. Construction of the jacket and the topside at the Bifab yard. Managed the Jacket construction planning scope • Provided new detailed estimation tools of the Load-out planned date, using production daily results (bracers and infills installed/welded out). • Optimized the schedule of the Rigging contractor and its interactions with production. Directed a team of 2 production planners • Trained the team to become proficient with Primavera P6. • Supported production team by identifying daily priorities and critical path. • Delivered daily production reports.

Market Place

No results found... (try selecting a different content filter)

Syndicate content