EPC Lead Planner, PREMIER OIL, Solan
START Date:
March, 2014
END Date:
September, 2014 Solan project.
Construction of the jacket and the topside at the Bifab yard.
Managed the Jacket construction planning scope
• Provided new detailed estimation tools of the Load-out planned date, using production daily results (bracers and infills installed/welded out).
• Optimized the schedule of the Rigging contractor and its interactions with production.
Directed a team of 2 production planners
• Trained the team to become proficient with Primavera P6.
• Supported production team by identifying daily priorities and critical path.
• Delivered daily production reports. Created and updated a close-out Punch list.
• Delivered weekly and monthly reports: progress, key dates, KPI, achievements.