AREVA NP

Commissioning & Startup Engineer, AREVA NP, Power Station Operation - Maintenance / Testing

START Date: 
July, 1995
END Date: 
December, 1998

Experience Hours (Planning & Scheduling): 
300

EPC Lead Planner, AREVA NP, EPR flammanville

START Date: 
November, 2005
END Date: 
December, 2011

Senior Schedule Manager

Client side senior planner, AREVA NP, Hinkley Point C EPR

START Date: 
September, 2011
END Date: 
November, 2015

Project schedule manager - New Power Plants

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
200

Project Controls Specialist, AREVA NP, Multiple Projects ; Oil and Gas / Nuclear / EPC Project Controls

START Date: 
May, 2007
END Date: 
April, 2015

·      Oversight of scheduling in AREVA Federal Services, including project schedulers, schedule processes and methodology, and schedule training

·      Develop & Maintain Project and Proposal Schedule

·      Conduct Schedule Quality Analysis utilizing Deltek Acumen

Business Development Manager / Project Controls Manager, AREVA NP, Nuclear Reload Projects

START Date: 
March, 1987
END Date: 
July, 2012

Project Controls Specialist / Contract Administrator

Scheduler (P3)

Experienced with MicroSoft suite of software.

Business Development Manager / Project Controls Manager, AREVA NP, Nuclear Reload Projects

START Date: 
March, 1987
END Date: 
July, 2012

Project Controls Specialist / Contract Administrator

Scheduler (P3)

Experienced with MicroSoft suite of software.