EPC Lead Planner, James Fisher Nuclear Limited, SGHWR
START Date:
September, 2020 Lead Planner - James Fisher Nuclear Ltd
- Took the lead for a number of programmes related to the delivery of a project to deconstruct one of the legacy R&D Reactors for Magnox
- Developed, with information I collated, a detailed construction programme that included a complicated Mechanical and Electrical installation phase.
- Rebaselined the contract programme with the civils and M&E installation sequence including the dependencies of the Safety Case Logic required ahead of major construction.
- Instigated a tracking system for the remaining design deliverables required for the completion of one of the safety cases critical for the completion of the programme.
- Built a relationship with the Client Senior Project Manager that led to a more trusting environment, which then drove the client to accept submitted programmes (there had been a culture of contradictory outputs which led to erosion of confidence in the ability to complete the scope of works)
Experience Hours (Planning & Scheduling):
2050
Experience Hours (Cost Management):
1100
Experience Hours (Forensic Analysis):
200 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: