Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Critical Path Analysis

EPC Lead Planner, James Fisher Nuclear Limited, SGHWR

START Date: 
September, 2020

Lead Planner - James Fisher Nuclear Ltd

  • Took the lead for a number of programmes related to the delivery of a project to deconstruct one of the legacy R&D Reactors for Magnox
  • Developed, with information I collated, a detailed construction programme that included a complicated Mechanical and Electrical installation phase.
  • Rebaselined the contract programme with the civils and M&E installation sequence including the dependencies of the Safety Case Logic required ahead of major construction.
  • Instigated a tracking system for the remaining design deli
Experience Hours (Planning & Scheduling): 
2050
Experience Hours (Cost Management): 
1100
Experience Hours (Forensic Analysis): 
200

PLANNING ENGINEER, MOTA-ENGIL, Dar es Salaam to Morogoro - SGR

START Date: 
February, 2018
END Date: 
January, 2019

Adjusted Construction Master Schedule to the available resources, Progress update, Daily Production/Planning meetings with construction teams, intervention on implementation of Last Planner System on this Project, Constraints forecast, Weekly Plans, Daily/Weekly and Monthly Reports.

Entitlement Plan and Delay Analysis to support Claims.

Planning and Cost Control of a multidisciplinary Project, including Earthworks with blasting activities, Bridges, Drainage, Railway and Building works

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Cost Control, PLANNING ENGINEER, Project Control, Bonatti S.p.A, CPF Construction, Site Camp Construction, WELLPAD

START Date: 
February, 2019

Planning Engineer and Cost Control / Project Control

Preparing schedules for tender and construction phases, progress updates, weekly plans, constraints forecast, daily production/planning meetings using KPIs, daily/weekly and monthly reports, Critical Path Analysis.

Earned Value Management and Cost control. Cost Reports, Earned Value Analysis and cost forecast.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
200

Planner, Trant Engineering, Fawley Refinery Maintenance

START Date: 
March, 2018

Outline:

Reporting to the Site Manager and our client ExxonMobil; I am responsible for the Planning all Civil Engineering projects for Trant Engineering at Fawley Refinery.

 

Key responsibilities:

Experience Hours (Planning & Scheduling): 
3400

Senior Project Control, KUWAIT INTEGRATED PETROLEUM INDUSTRIES COMPANY (KIPIC), Al-Zour Refinery Project (ZOR)

START Date: 
October, 2016
  • Develop preliminary schedules and establish key dates for all phases of EPCC Projects including tendering, FEED and execution
  • Organize, monitor, control and ensure delivery of the Program Master Schedule / Program Management Plan for all Packages EPC, including the integration Program Master Schedule
  • Supervise, monitor and inspect contractors' work during the contract execution to ensure compliance with the terms and conditions of contract, and report any discrepancy between contract and actual work
  • Interact with project team to define scope of work to develop a
Experience Hours (Planning & Scheduling): 
1450
Experience Hours (Cost Management): 
450
Experience Hours (Forensic Analysis): 
1500

Freelance Planning Consultant, NSW, Sydney, Australia

START Date: 
June, 2013

Freelance Planning Consultant

  1. Development of custom Excel spread sheets.
  2. Updating schedules (Primavera, MSProject)
  3. Critical Path Analysis
  4. Allocation and distribution of resources.
Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Forensic Analysis): 
1000

3D / 4D Planning Engineer, genesis manazil group, Building

START Date: 
August, 2013
END Date: 
July, 2016

As planning Engineer responsible for all the planning, scheduling, Reporting and many other works.

3D / 4D Planning Engineer, National Grid UK, Electricity Transmission Substations and OHLs

START Date: 
November, 2010
END Date: 
March, 2017

·         Assured Contractor’s programme after contract awarded based on planning principles, Transmission Procedure 193, mandatory milestones, outages, links, budgeted cost and WBS mapping.

·         Ensured Contractor’s programmes are fit for NEC3 type of contract – Option A –E.

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
4000

Planning Lead, Costain integrated Services Ltd, National Grid - Transmission Services Gas Commission

START Date: 
July, 2015

My Daily duties have me working on around 50 programmes split between 4 delivery engineers. I am responsible for critical path reporting, updating the programmes with the information from the delivery engineers, cost loading and keeping track of any and all costs associated with the programme by way of forecasting, accruing and actualising costs in line with information gathered from our team of QS's.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200

Planning Lead, Costain integrated Services Ltd, National Grid - Transmission Services Gas Commission

START Date: 
July, 2015

My Daily duties have me working on around 50 programmes split between 4 delivery engineers. 

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200

Market Place

No results found... (try selecting a different content filter)

Syndicate content