Planning Manager, Claims Consultant, Bid Manager, Postlewhite Project Planning Ltd, Various Projects

START Date: 
July, 2005
END Date: 
July, 2008

Postlewhite Project Planning (self-employed)

 

Various contracts

  • Supporting production of defence documents on large earthworks claim –producing detailed analysis of earthworks movements; producing presentations and analyses for legal team
  • Supporting production of Tender submission with BMI healthcare – producing construction programme; producing overall mobilisation pr

Planning Manager, Amey Construction Ltd, M6/M74 Upgrade to Motorway Standard

START Date: 
March, 1997
END Date: 
September, 1998

 

M6/M74 Joint Venture – Upgrade to Motorway Standard

Design Build Finance and Operate Joint Venture between Amey, Sir Robert Mc Alpine, Taylor Woodrow and Barr.  Multi-disciplined contract with major Geotechnical aspects with high profile environmental issues.  Involved construction of 20km of new green field dual 3 lane motorway and 11km of symmetrical widening of the existing

Planning/Estimating/Site Engineer, Winner Sports International Ltd, Enugu, Nigeria., Dick Tiger Memorial Gymnasium Enugu $1.0million USD

START Date: 
September, 1987
END Date: 
June, 1988

1987-1988 Site Engr  Winner Sports International Ltd, Enugu, Nigeria.

Project Executed

(i) Dick Tiger Memorial Gymnasium Enugu $1.0million USD

 

Planning and Project Controls Manager, Jarvis Rail, Rugby Remodelling

START Date: 
January, 2008
END Date: 
November, 2009

Planning & Project Controls Manager

Leading planning and project controls teams on the multi disciplined Rugby Remodelling Project

Planning Manager, BAM Nuttall, evergreen 3

START Date: 
March, 2010
END Date: 
August, 2010

Planning Manager

Leading the planning and project control functions on the multi disciplined Evergreen 3 project

Area Planning Manager, Murray & Roberts (Middle East), Burj Al Arab

START Date: 
June, 1997
END Date: 
February, 2000
  • Employed as Planning Manager for Murray & Roberts Contractors (Middle East) LLC performing both Head Office & on site planning roles.  Based in Dubai, UAE.
  • Burj Al Arab – World’s tallest hotel.  Joint managed both the tender & pre-contract negotiation & cash flow analysis, controlling a staff of five.    Contract value $1b.
  • Airport Arrivals Terminal Dubai – 800m long portal frame building.   Responsible for planning at tender & pre-award negotiation stages following through wi

Bid Manager - Chief Engineer, Johnston International, Various Construction Projects

START Date: 
September, 2005
END Date: 
April, 2007

BID MANAGER – CHIEF ENGINEER

Employed by Johnston International Limited a Caribbean wide  General Contractor.

Responsible for Bid Management on a variety of projects in the value range of $10m to $100m such as a PFI hospitals, Government Office Buildings, Offices, Marine Works, Hotels, Airports, Condominium and Resort Developments.

Projects where spread over various Caribbean Islands.

Carried out planning functions when resources were unavailable 

Senior Planning Manager, OHL International, Tenders and Mega Projects

START Date: 
February, 2010

Current Role

 

Currently Bid and Planning Manager for OHL International responsible for the Middle East and beyond

Core senior Planner, Dar Al Handasah (Shair & Partners), JUMEIRAH VILLAGE

START Date: 
February, 2006
END Date: 
February, 2011

 

Planning Consultant, GM, masterspmc.com, High End Residential Towers, Hotels %26 Retial, Commercial Parks, institutional, Urban Re-development

START Date: 
January, 2005
END Date: 
March, 2011

Key role: Planning and Operations

For the sites across India i.e. Mumbai, Hyderabad, Delhi & Bangalore

Market Place