Lead/Senior Planning Engineer, Petrofac Emirates LLC, GASCO NGL-4 Project Ruwais Abu Dhabi United Arab Emirates

START Date: 
October, 1998
END Date: 
August, 2013
As a Lead/ Senior Planning / Scheduling Engineer these are my duties and responsibilities: *Develop Engineering, Procurement & Construction (EPC) Schedules (Level II, III, & IV) & in accordance with the work breakdown structure. *Prepare Pre-com., Commissioning, & Start-up Schedules (Level IV). *Prepare Project Cost analysis, Claims, & Identifies critical activities, floats and slipped activities. *Prepare Progress measurement sheets, Weekly Commodity & Manpower reports. *Prepare all necessary Graphs (“S” curves, Skyline, Histogram etc.) required for the project.

Planning Engineer, Descon Engineering Limited Pakistan, BYCO oil refinery

START Date: 
December, 2008
END Date: 
December, 2012
  • Preparation of Execution level-3 & level-4 plans on Primavera Project Planner, Indirect and direct manpower deployments.
  • Monitor progress of piping to ensure that the project is progressing as planned and the targets would be met and raise flags if the targets are likely to slip.

Regional Director, Freedom Group of Companies, Various

START Date: 
October, 2012

Has over fifteen years’ project and contract management, four year’s operations management and now regional director experience. He has delivered a wide portfolio of building, engineering and IT projects with values up to £140m, including power infrastructure, gas distribution and transmission, along with the delivery of new build office, hotel and retail accommodation. Kenny has a strong proven track record in all aspects of the project management life cycle, enhanced by an MSc in Project Management. 

Assistant Construction Planner, MASA, Production Facilities - Pipelines

START Date: 
June, 2012

Planner and controller from a leading construction and operations company in Colombia

Site Planner, Al Bassami Group, Salman Bay Infrastructure Project

START Date: 
June, 2007

 

PROFESSIONAL WORK HISTORY

Company: Al-Bassami Group

Head Office

 (January 2012 – October 2012)

-          Technical Head

·         Compiling of All Report to all Projects

Site Planner, Al Bassami Group, Salman Bay Infrastructure Project

START Date: 
June, 2007

 

PROFESSIONAL WORK HISTORY

Company: Al-Bassami Group

Head Office

 (January 2012 – October 2012)

-          Technical Head

·         Compiling of All Report to all Projects

Project Controls & Planning Manager, Control & Applications Emirates, Becrel, Alstom, ABB, EEPL, Multiple

START Date: 
June, 1991
Introduction

A Project Controls Manager with more than 20 years of rich experience in various fields (2 Year in Mining Industry, 11 Years in Power Sector & 7 Years in Oil & Gas Industry) is currently associated with CAE -Abu Dhabi since Apr-2007.

 

Present Job Profile:

 

Present Position– Project Controls & Planning Manager

 

Planning Engineer, SALUM, EARTH DAM

START Date: 
September, 2012
END Date: 
June, 2013

Planning Engineer (on site) - Responsible for:

(1) planning and scheduling activities related toan earth dam construction (which belongs to VALE – very large global mining company);

(2)liaising and coordinating with on-site personnel to achieve continuous improvement in meeting quality, environmental, health and safety requirements;

Planning & costing Engineer, TSM, Mechanical Construction

START Date: 
September, 2011
END Date: 
June, 2013

 

Qualification

 

·         Masters in Industrial Management (MEM) (2012) from NED University of Engineering & Technology, Karachi – Pakistan, (CGPA of 3.56) with the following major courses

 

Design Engineer, Oil Reach Company, Design of Engineering Components like Impeller

START Date: 
October, 2008
END Date: 
January, 2011

Oil Reach Company – Glasgow, United Kingdom

·         Designed Pneumatic Gripper and Linear Actuator in connection with rotary benders technology – achieved design objective by satisfying high strength and mobile outdoor applications

·         Interfaced with new product and process development group on proposal, requirements, design and validation