Burj Al Arab

Construction Project Planner / Senior Planner, Al Habtoor Engineering Enterprises, Burj Al Arab, Carlton Hotel, Holiday Inn Hotel, Marina Mall

START Date: 
April, 1990
END Date: 
April, 2000

Senior Planning & Controls Engineer for a reputed Contracting Company - AL Habtoor Engineering wherein I was involved in Planning of world famous structures like Burj Al Arab which is a 7 star hotel and Marina Mall which is a modern shopping complex with more than a million square feet retail space.Also involved in Planning, monitoring and control of 30+ stories towers for Holiday In Hotel.

Heading a team of 4 planners and responsible for development of Baseline schedules, montoring and reporting.

Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Cost Management): 
9000
Experience Hours (Forensic Analysis): 
2500

Area Planning Manager, Murray & Roberts (Middle East), Burj Al Arab

START Date: 
June, 1997
END Date: 
February, 2000
  • Employed as Planning Manager for Murray & Roberts Contractors (Middle East) LLC performing both Head Office & on site planning roles.  Based in Dubai, UAE.
  • Burj Al Arab – World’s tallest hotel.  Joint managed both the tender & pre-contract negotiation & cash flow analysis, controlling a staff of five.    Contract value $1b.
  • Airport Arrivals Terminal Dubai – 800m long portal frame building.   Responsible for planning at tender & pre-award negotiation stages following through wi