Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Version 6.2.1 - Original Durations Changes

2 replies [Last post]
Jon Ward
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60

Hi all,

 

As always – any assistance or ideas on this would be very much appreciated.

 

The scenario is as follows :

  • We have a project held on a central server, that is located within an Enterprise (EPS) node with its own current baseline
  • Other projects are held on the same server, however these are located in their own dedicated EPS nodes
  • This morning we have noticed that on most (nearly 7.6k activities) Task Dependant activities the Original Durations have (in some instances) moved considerably, for example the Original Duration is 2 days, however the Start Date =  21-Jan & Finish = 30-Jan,, while we are not concerned about the dates (as these are where they should be, we are concerned about the changes in the Original Durations
  • These changes in Original Durations are the same in the baseline also, as mentioned – the dates allocated to each activity have NOT changed but the Original Durations have changed
  • We have since F5’d and noticed that the Original Durations are back to where they should be (in most instances)
  • This is a resourced loaded schedule, the resources are on the correct Calendar, the calendar has not been amended in any way and shows the correct / expected working times,, the changes in durations make the length of the activity (start and finish) not equate to the ‘work time’ as per the calendar

 

 

Has anyone ever experienced this?

Replies

Raymund de Laza
User offline. Last seen 14 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Jon,

Make sure the Calendars used in the Activities is the same as the Default Calendar.

Shah. HB
User offline. Last seen 41 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Jon Ward

Check the the duration type from activity details and choose the option fixed duration and units

Cheers

Shahul