Planning, Claims & Contracting
Dear All,
I want to Know how many of days i need to claim the owner from the Schedule.
I checked the document dates from Qc/Dc.
Then I filterd the Activities Which delayed more than 14 days as contracts conditions
1. then i supposed to add these duration to every relative items, or as a lag in the relations between activities (the question here what the right way of previous two?)
2. if i found three issues delayed one activity (what is the right in that case 1> collecting duration for the three and add for the concerned activity or 2< checking the over lap between the three and add just the over lap duration between the three issues.
example : event (A) Delayed the activity 5 days from 1-jan-2013 to 6-jan-2013
event ( B) Delayed the Activity 6 days from 2-jan-2013 to 8-jan - 2013
Event (C) Delayed the Activity 5 days from 4-jan-2013 to 9-jan 2013
If i collection all my right durations it will give the right to add (5+6+5) = 16 days the first way
If i take just the over lap between the three events it will give the right to add just the duration between 1- jan 2013 to 9 jan 2013 = 8 days the 2nd way
what is the right way of two