Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Original Duration change equal to Remaining Duration???

No replies
xadlim B.
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 4 Feb 2012
Posts: 25

 

 Need help please.... Why is it that Original Duration in the Summary Level will change equal to Remaining Durationafter I update some activities??? Due to this reason my Duration % Complete in the Highest or Project Level will always be 0% since Duration % Complete is computed based in the formula D%= (Original Duration (Current Duration) - Remaining Duration / Original Duration (Current Duration) * 100.  Thanx for your input.