Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2015-04-08 18:29 Permalink go to enterprise calendars go to enterprise calendars and create a new calendar now go to activities add a column for calendar (its under general) click in the calendar column change the first one in that column to the new calendar that you just added. now hold the shift key and click on the last activity and make sure all activirtes are highlighted right click and select fill down press f9 and rescheduel the project go to the projects directory and make sure that your project is highlighted click on the defaults tab and on the right select the new calendar that you just added now when you add a new activity it will ue the newly created calendar. the duration of the lag does not change unless YOU change it. Member for 14 years 10 months Member for 14 years 10 months Submitted by mrson1982 on Wed, 2015-04-08 06:43 Permalink I want to focus on Lag I want to focus on Lag duration, because it will follow predecessor activities Calendar, and when predecessor activities change Calendar, it will change also, i dont know how to keep it as original Lag duration... Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2015-04-08 18:29 Permalink go to enterprise calendars go to enterprise calendars and create a new calendar now go to activities add a column for calendar (its under general) click in the calendar column change the first one in that column to the new calendar that you just added. now hold the shift key and click on the last activity and make sure all activirtes are highlighted right click and select fill down press f9 and rescheduel the project go to the projects directory and make sure that your project is highlighted click on the defaults tab and on the right select the new calendar that you just added now when you add a new activity it will ue the newly created calendar. the duration of the lag does not change unless YOU change it.
Member for 14 years 10 months Member for 14 years 10 months Submitted by mrson1982 on Wed, 2015-04-08 06:43 Permalink I want to focus on Lag I want to focus on Lag duration, because it will follow predecessor activities Calendar, and when predecessor activities change Calendar, it will change also, i dont know how to keep it as original Lag duration...
Member for
16 years 3 monthsgo to enterprise calendars
go to enterprise
calendars and create a new calendar
now go to activities add a column for calendar (its under general)
click in the calendar column change the first one in that column to the new calendar that you just added.
now hold the shift key and click on the last activity and make sure all activirtes are highlighted
right click and select fill down
press f9 and rescheduel the project
go to the projects directory and make sure that your project is highlighted
click on the defaults tab and on the right select the new calendar that you just added
now when you add a new activity it will ue the newly created calendar.
the duration of the lag does not change unless YOU change it.
Member for
14 years 10 monthsI want to focus on Lag
I want to focus on Lag duration, because it will follow predecessor activities Calendar, and when predecessor activities change Calendar, it will change also, i dont know how to keep it as original Lag duration...