Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Doubt in Duration

1 reply [Last post]
Jithin Kambhikanam
User offline. Last seen 28 weeks 6 days ago. Offline

Helo All,

What error am I doing.

 

The below pic shows the duration of the activity and WBS

  WBS Total570
PrimaveraStart Finish 
Activity A13-Apr-2329-May-2330
Activity B30-May-232-Aug-242954
Activity C3-Aug-2416-Sep-2445

 

But the same thing if I put it in excel gives me this duration.

ExcelStart Finish 
Activity A13-Apr-2329-May-2347
Activity B30-May-232-Aug-24431
Activity C3-Aug-2416-Sep-2445
  Excel Total523

I would like to show the excel duration in the schedule 

 

The calendar for 1st activity = 8 Hrs X 5 Days and the other 2 activity = 8 Hrs X 7 Days

Please guide me.

 

Thanks 

Jithin

Replies

Zoltan Palffy
User offline. Last seen 23 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

because the schedule is based on 8 hours per day based on the calendar

excel does not consider TIMES it is just a day for day calculation

P6 uses times in the background

Jithin Kambhikanam
User offline. Last seen 28 weeks 6 days ago. Offline

Hi All,

 

The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table.

 

So why is it like that?