Helo All,
What error am I doing.
The below pic shows the duration of the activity and WBS
WBS Total | 570 | ||
Primavera | Start | Finish | |
Activity A | 13-Apr-23 | 29-May-23 | 30 |
Activity B | 30-May-23 | 2-Aug-24 | 2954 |
Activity C | 3-Aug-24 | 16-Sep-24 | 45 |
But the same thing if I put it in excel gives me this duration.
Excel | Start | Finish | |
Activity A | 13-Apr-23 | 29-May-23 | 47 |
Activity B | 30-May-23 | 2-Aug-24 | 431 |
Activity C | 3-Aug-24 | 16-Sep-24 | 45 |
Excel Total | 523 |
I would like to show the excel duration in the schedule
The calendar for 1st activity = 8 Hrs X 5 Days and the other 2 activity = 8 Hrs X 7 Days
Please guide me.
Thanks
Jithin