Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Progress reporting

Planner, Magnox, Sizewell A Power Station

START Date: 
April, 2005
END Date: 
April, 2008

Planner responsible for developing and reporting on full site plifecycle plans across Operations, Defuelling, Conventional decommissioning, ILW Management, Waste Retrieval & Processing

Head of Scheduling, Magnox, Sizewell A Power Station

START Date: 
April, 2008
END Date: 
March, 2010

Responsible for a team of 11 planners across four departments

Ensuring all scheduling carried out on site meets all the companies and customers standards and procedures.

Integrating project schedules with maintenance work week planning and all levels of schedule up to the site Milestone Sequence Chart

Head of Scheduling, Magnox, ILW Management

START Date: 
April, 2010
END Date: 
March, 2012

Head of Scheduling for the ILW Management Programme within Magnox Ltd.

Developed a business case and revised baseline for eight sites utilising new technologies.

Head of Scheduling, Strategic Programmes, Magnox, Magnox Optimised Decommissioning Plan

START Date: 
April, 2012
Head of Scheduling for Strategic Programmes within Magnox Ltd - assisted in developing our assurance model and carries out assurance reviews of all programme baseline changes prior to insertion. Currently leading transition to full managed service for Project Controls within Strategic Programmes Production of Milestone Sequence Charts for each individual programme, production of high level graphics for each individual programme. Resource management of all planning resource allocated to Strategic Programmes

Planning Engineer, Celiks IS LLC, University of Nizwa Main Capus

START Date: 
July, 2006
END Date: 
February, 2013
WORK EXPERIENCE March 2012 – Till Present Planning Engineer Celik Is LLC, Oman Responsibility  Breaking down the construction activities into progress measurable elements.  Preparing Site Instruction impact analysis for claiming Extension of Time.  Involved in the preparation of revised construction schedule.  Contribute in preparing narrative summary for progress reports.  Preparing progress monitoring formats for site engineer and supervisors reports.  Follow-up of with deliverables (materials and drawings) and their impact on the schedule.  Prepare Look Ahead Schedules to

Planning Engineer, Celiks IS LLC, University of Nizwa Main Capus

START Date: 
July, 2006
END Date: 
February, 2013

 

WORK EXPERIENCE

March 2012 – Till Present

Planning Engineer

Celik Is LLC, Oman

Responsibility

 B

reaking down the construction activities into progress measurable elements.

Planning and Schedulling, Iberdrola Engineering&Construction, 1200 MW Coombined Cycle Power plant

START Date: 
September, 2008
END Date: 
June, 2012

Planning , schedulling , wbs update, earne value management, monitoring, S curve, BCWS, ACWP, BCWP

senior time scheduling engineer, THOST Projektmanagement GmbH for AE&E Inova and IHI Euro Power GmbH, Power Plant 850MW

START Date: 
August, 2010
END Date: 
September, 2012

Senior Project Engineer for Powerplant Erection in Germany

responsible for contractual items of boiler, flue gas cleaning, boiler house (steel, concrete), coal handling

Size of schedule: round about 6000 activitys

Planning of commissioning schedule.

Progress report to project manager, client, head of company

S-Curves for critical items

Detail Planning of boiler welding, Critical Erection Items

schedule analysis of sub contractors schedule and contracts

 

Alliance Planner & Scheduler, Visser & Smit Bouw, Gas Storage Bergermeer and Boekelermeer Alkmaar

START Date: 
April, 2012
Planner of the civil works activities, Steelstructure, UG Piping and E&I installation (€60mln) for Visser & Smit Bouw at TAQA Gas Storage location Bergermeer and Boekelermeer. Start from april 2013 - ........ Contractplanning, Base Line Schedules, Six Weeks Look Aheads. Engineeringsplanning and Work Preparation planning. Progress Reporting Engineering, Work Preparation, Base Line and Recovery plan.

Project Manager, Balfour Beatty Power Networks Ltd, Various UK and other

START Date: 
January, 1991
END Date: 
February, 1996
Project engineer, project Manager on various overhead powerline projects from 11kV to 400 kV; new build, refurbishment and replacement. UK focused but deployed to projects in Germany and Cyprus for short projects. Also managed fibre optic installation on OHL networks.

Market Place

No results found... (try selecting a different content filter)

Syndicate content