Checking Subcontractors invoices
START Date
Wed, 02/01/2017 - 01:00
END Date
Thu, 11/01/2018 - 01:00
In charge of the preparation of a baseline network analysis programme complete with resource loading.
Recording and reporting the actual progress of the work versus the planned work in P6 and RMS 3.0 system.
Monitoring all activities in the project schedule for potential delays, and regularly update claims and variation logs.
Prepare the 3 weeks look-ahead schedule for weekly coordination meeting
Prepare the monthly progress report and the monthly interim progress payment.
Prepare the Time Impact Analysis and other necessary substantiation
START Date
Mon, 12/01/2008 - 01:00
END Date
Sat, 12/01/2012 - 01:00
Preparation of Execution level-3 & level-4 plans on Primavera Project Planner, Indirect and direct manpower deployments.
Monitor progress of piping to ensure that the project is progressing as planned and the targets would be met and raise flags if the targets are likely to slip.
START Date
Tue, 03/01/2011 - 01:00
END Date
Thu, 03/01/2012 - 01:00
POGC – South Pars Gas Field Development Phase 11
Cost Estimation for Basic Design of Camps, Site preparation, Geotechnical Survey, EPC1, EPC2 & EPC3 Tenders.
Reviewing the ITB of above mentioned tenders and Tenders Technical Evaluation Team Member.
Review and comments on FEED documents prepared by China Petroleum Engineering Company (CPE) with Mott Macdonald as Endorsement Third Party.
Preparing the Onshore Portion Weekly & Monthly Report.
Preparing the Onshore Portion Look ahead and Catch up plan.
Checking and a