Client side senior planner, AREVA NP, Hinkley Point C EPR

START Date: 
September, 2011
END Date: 
November, 2015

Project schedule manager - New Power Plants

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
200

Construction Planning Consultant, PETROLEO BRASILEIRO S.A. - PETROBRAS - STEI SERVIÇOS TÉCNICOS, Construction Project of the Abreu e Lima Refinery

START Date: 
June, 2014
END Date: 
July, 2015
  • Responsible for ensure together with the Planning Engineer to integrate all the schedules of the construction Project of the Abreu e Lima Refinery.
  • Application the checklist in the schedules submitted by contractors to ensure the quality and integration of it.
  • Preparation of Physical Advancement curves and management reports to the Directors and the President of Petrobras.
  • Preparation and review of planning procedures..
  • Integration of all Project schedules by checking the interfaces between units and evaluating the impacts.
  • Realization the 4D Pla
Experience Hours (Planning & Scheduling): 
2000

Construction Project Planner, PM Group, MedImmune

START Date: 
August, 2012

Construction Project Planner on pharma project for MedImmune in Speke, Liverpoool