Project Planning Engineer, Murray and Roberts Australia, Australia, Barrow Island, GORGON LNG Project, Pioneer Material Offloading Facility

START Date: 
June, 2010
END Date: 
September, 2012

Project Planning Engineer

June 2010 – October 2012 PMOF, Gorgon LNG Project, Barrow Island

Lead Planning Resource for design, procurement & construction of marine/ offshore materials offloading facility. AUD 500 million

Senior planner, GS E&C, Ha Noi - Hai Phong expressway project

START Date: 
July, 2008

Current Project: Ha Noi - Hai Phong Expressway project - Viet Nam

Role: - Planning staff

        - Preparing report for construction works

        - Preparing BoQ for sub contract

        - Negotiation unit price with sub contractor

        - Calculate of escallation

        - Preparing document for claim of extension of time

Planning Manager, beard swindon, , Various

START Date: 
August, 2003
END Date: 
August, 2013

Planning Manager with 10 years experience in Construciotn planning, tendering and client monitoring

Senior Project Controller, BAE Systems, not disclosed

START Date: 
January, 2011
END Date: 
September, 2011

Project based Programme Management Office (PMO) role in a large value software and hardware development project transitioning from construction to service phase

Working alongside Project Management, Engineering and Finance functions, taking responsibility for the

Deputy Project Manager, BAE Systems, Aircraft Carrier Alliance

START Date: 
March, 2009
END Date: 
January, 2011

Deputy Project Manager in a major multi billion pound industry and MoD partnership project, transitioning from Design to Construction Phase

Delivering Project Management functional excellence by ensuring Level 3 Schedules align with the Statement of Work (SOW), c

Lead Master Planner / Scheduler, Lockheed Martin, not disclosed

START Date: 
September, 2011
END Date: 
July, 2013

Lead Planner in a schedule critical project.

Responsible for the setup and onward management of full EVM analysis along with management of the IMS baseline in a fully resourced, networked, event-driven schedule.

Project Controls Engineer, ANSAQ Contracting Company, Multiple Project - Programs

START Date: 
July, 2008
END Date: 
September, 2014

•        Involve in program management, supporting different project managers handling different projects at the same timeline. Develop the schedule management plan and schedule design for the assigned projects, facilitate the development of master construction schedule.

Experience Hours (Planning & Scheduling): 
9000
Experience Hours (Cost Management): 
7000
Experience Hours (Forensic Analysis): 
2000

Interim Contracts Manager, Mott MacDonald Limited, Thames Water - Networks - Flood Alleviation

START Date: 
July, 2013

Interim Contracts Manager managing flood allevation programme for Thames Water Networks in the London Region using the ICHEME Burgundy Book.

Planning Executive, MMC Gamuda Joint Venture Sdn Bhd., Electrified Double Track Project (Ipoh - Padang Besar)

START Date: 
July, 2010

Responsibilities

1. Support Planning Manager (Overall/Track) and Planning Manager (Infra) with all baselines & forecast planning / interfacing.

Planning Engineer, DESCON Engineering Qatar L.L.C, PMP

START Date: 
November, 2011
END Date: 
June, 2013

·         Preparation of baseline program master schedule base on project requirements and perform critical path analysis;

·         Analyze the work statements and drawings for preparation of level IV activity networks in order to calculate the require resource for smooth execution of project;

Market Place