Senior Planner, Kier infrastructure, Sellafield & M6 Smart Motorway

START Date: 
May, 2017
END Date: 
July, 2018

Working on nuclear and then a Smart motorway.

Using P6 to progress and report on for the Nuclear role, establishing a Cl31 agreed programme for the smart motorway and the providing progress. Senior Planner

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Forensic Analysis): 
50

Planning Engineer, MOTA-ENGIL, Road infrastructures for Malawian Government

START Date: 
December, 2017
END Date: 
March, 2018

Successfully assisted Project Managers to schedule three critical Projects, optimizing resources and reporting methods

Planning, Progress update, Projects Control

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
0

Planning Manager, Vinci - Taylor Woodrow, Cross Rail / Bexhill - Hastings Bypass

START Date: 
October, 2013
END Date: 
December, 2014

Crossrail

Victoria Dock Portal - Construction Programme, Progress, Dash Boards, CEs

Totenham Court Road - M&E programme  update and CEs

Bexhill to Hastings

Rebaseline of programme, CEs, weekly programmes, programme updates

 

Experience Hours (Planning & Scheduling): 
550
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
50

Head of Planning, Larsen & Toubro, Various

START Date: 
January, 2015
END Date: 
June, 2017

Head of planning supervising a team of 30 No planners across Power / water / sewage / rail / roads and building

Gold Line / Foot ball stadia Al Rayyan / Al Wakrah bypass / substation various / Red Line M&E tender / Idris scheme / Industrial Area / Dubai Rain water storage / Oman hospital

Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
300

Head of Planning, Larsen & Toubro, Various

START Date: 
January, 2015
END Date: 
June, 2017

Head of planning supervising a team of 30 No planners across Power / water / sewage / rail / roads and building

Gold Line / Foot ball stadia Al Rayyan / Al Wakrah bypass / substation various / Red Line M&E tender / Idris scheme / Industrial Area / Dubai Rain water storage / Oman hospital

Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
300

Head of Planning, Larsen & Toubro, Various

START Date: 
January, 2015
END Date: 
June, 2017

Head of planning supervising a team of 30 No planners across Power / water / sewage / rail / roads and building

Gold Line / Foot ball stadia Al Rayyan / Al Wakrah bypass / substation various / Red Line M&E tender / Idris scheme / Industrial Area / Dubai Rain water storage / Oman hospital

Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
300

Associate Planning Manager, WSP, Highways England - Various

START Date: 
July, 2017

Working on Smart Motorways as CA and PMO planner - M27 J4 to J 11

A19 Coastal Road, A19 Testos

RIP Midlands 

CIP - LTC /A303

Kara Tower

Red Sea Airport Preliminary Design

Claim - Hounslow Highways

Experience Hours (Planning & Scheduling): 
650
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
50

Planner, Lakesmere, Windermere Steam boat museum

START Date: 
June, 2016
END Date: 
April, 2017

1st Planning role. Completing tender programs and progressing as-built programs on various faced & roofing contracts

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
50

Technical Manager, Kharafi National, department manager

START Date: 
July, 2017
Head of planning and cost control department managing all projects
Experience Hours (Planning & Scheduling): 
6050
Experience Hours (Cost Management): 
6600
Experience Hours (Forensic Analysis): 
9500

Engineer / Project Engineer, moblize, Real time drilling monitoring

START Date: 
January, 2015

sadsadsdsadsadsa sdsadsad sdasdsad sdasdsasds fef refer fer ftrg rtg rtg r g5 4g r v rf erfbehfenjvnhjerv erfbhe ehbvhe hjrbfhjef ehfrebfeh bfhebrfe fhefbef eijfhne feiurfbe fekfberfefbefe trgrg t grg 4g

Experience Hours (Planning & Scheduling): 
2750
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
500