Sr Project Planner, Civmec Construction & Engineering Pty Ltd., Australia, Barrow Island, Exmouth Basin offshore, Gorgon Downstream LNG Project, Nelson Point & Finucane Island Expansion, Pilbara Region, WA; Coniston Subsea Manifold Plem, Western Australia

START Date: 
October, 2011
END Date: 
February, 2013

• Prepare tender proposal, fabrication and modular assembly works schedules.
• Develop baseline schedules in Primavera P6 as per scope of work.
• Maintain and update multiple schedules.
• Liaise with construction and engineering team for progress update and produce weekly / monthly progress reports.
• Provide monthly data to cost controller and project manager for cash flow forecast.
• Forecast on manning requirements provided to upper management on a regular basis.
• Perform critical path analysis and highlight any deviations to project manager.

Project Planning Engineer, Murray and Roberts Australia, Australia, Barrow Island, GORGON LNG Project, Pioneer Material Offloading Facility

START Date: 
June, 2010
END Date: 
September, 2012

Project Planning Engineer

June 2010 – October 2012 PMOF, Gorgon LNG Project, Barrow Island

Lead Planning Resource for design, procurement & construction of marine/ offshore materials offloading facility. AUD 500 million

Senior Planning Engineer, Leighton Contractors Pty Ltd, Gorgon LNG Civils & U/G Services, Barrow Island, WA

START Date: 
October, 2011
END Date: 
September, 2012

Duties & Responsibilities

  • Assist Area Manager/Project Engineer in development of Level 4/5 detailed construction Schedule.
  • Monitor Level 4/5 Schedule implementation and generate out-of-sequence activity report.
  • Directly responsible to the Planning & Controls Manager in maintaining the Primavera P6 Construction Schedule on site.
  • Monitor, analyse and review program performance outcomes for area of responsibility and recommend corrective action where necessary.
  • Gather construction progress data inputs and reports from Area M