Baseline Target Schedule

2 replies [Last post]
Mary Lou Horton
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 20 Oct 2010
Posts: 12
Groups: None

I am using P6 V6.2. When I create a baseline using Create from Current Schedule it is not saving the latest / current schedule. Every month I need to generate snapshot target or new baseline of this month status. We use this to measure variance between each progress update. Is there a trick? (I was able to do this all the time with V7). Is there a toggle that I need to turn on/off?

Replies

Ron Beechey
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 13 Jun 2002
Posts: 61

Mary

Under Admin Preferences tab Earned value under Earned Value Calculations make sure you have "Budgeted values with current dates" selected.

 

Hope this also helps

Daniel Limson
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Mary,

To create a baseline, go to projects then follow this sequence, Maintain basleine, Assign baseline and then go to your Bars icon and tick either your primary or secondary baseline bar depending on what you need to see.

Regards,

Daniel