Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How do I show "Actuals / early dates" from the baseline file - put the file as target but actuals not correct.

No replies
John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

How do I show "Actuals / early dates" from the baseline file - put the file as target but actuals not correct.

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read the post I am replying to if you want to keep your sanity as a scheduler.  I know I ask too many questions on this site - most of which do not get answered, and I do not supply enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser, all good, but this one was a gem.
 

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read this if you want to keep your sanity as a scheduler, actually the post I am commenting about.  I know I ask too many questions on this site, with not enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser but this one was a gem.

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read this if you want to keep your sanity as a scheduler, actually the post I am commenting about.  I know I ask too many questions on this site, with not enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser but this one was a gem.

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read this if you want to keep your sanity as a scheduler, actually the post I am commenting about.  I know I ask too many questions on this site, with not enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser but this one was a gem.

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read this if you want to keep your sanity as a scheduler, actually the post I am commenting about.  I know I ask too many questions on this site, with not enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser but this one was a gem.

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read this if you want to keep your sanity as a scheduler, actually the post I am commenting about.  I know I ask too many questions on this site, with not enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser but this one was a gem.

John Reeves
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Read this if you want to keep your sanity as a scheduler, actually the post I am commenting about.  I know I ask too many questions on this site, with not enough answers to others.  I will try to do better - but that information you provided is some of the best information I have ever received on this site.  Thank you so much.  It defied logic that I could not pull that information and you solved it.  The default settings must be to use the planned dates which is insane.  I have used earned value, but not through P6 so I would not have figured this out.  Rodel Marasigan is the site hero for the day, they will sing songs about you in the mountains.  Zoltan Palffy seems the most active wisdom dispenser but this one was a gem.

Zoltan Palffy
User offline. Last seen 18 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that is correct is it is mantain baseline then assign baseline

Rodel Marasigan
User offline. Last seen 9 weeks 42 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699

You have to maintained and assign baseline (either Project or Primary). Make sure that the Project settings is selected the Project Baseline or User's Primary Baseline (whichever the baseline is assigned). Change the Admin Settings on Admin Preferences --> Earned Value Tab --> Earned Value Calculation to Budgeted Values with Current Date or At Completion Values with Current Date.

Once done, you should be able to show the column with BL Project Start and BL Project Finish if set to Project Baseline (or BL1 Start and BL1 Finish if set to User's Primary Baseline) containing the Current Date of the Baseline. You can also select BL Project Actual Start/ BL Project Actual Finish, BL Project Early Start/ BL Project Early Finish..etc..