Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to send a copy as target baseline

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 26 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi,

When we export a project , the assigned baseline is not exported along with the project......So how to send a program to different user with the assigned baseline program intact???? Is it possible.......

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
You need to detach the baseline and restore then export together with current project and will create only one xer then if emailed to someone inform the recipient to attach the baseline after importing.