Budgeted Quantities being divided by hrs when importing

Hi Everyone

When I import a XER file sent to me and open it up, the budgeted quantities in the resources has changed – after some investigation I realised each time I import it is dividing the budgeted quantities by 8 – I presume this is because there are 8 hours in the day in the calendar.

Can anyone please advise how this can be avoided?

 

Thanks

M
Mike Testro 👤 Member for 20 years 7 months

Hi David

P6 is a pig to operate - it may be that you are set to hours and not days or something like that.

In ASTA you can just copy / paste directly from excell.

Why not multply by 8 before importing.

Best regards

Mike Testro