Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Budgeted Quantities being divided by hrs when importing

1 reply [Last post]
David Murphy
User offline. Last seen 12 years 9 weeks ago. Offline
Joined: 17 Oct 2008
Posts: 6

Hi Everyone

When I import a XER file sent to me and open it up, the budgeted quantities in the resources has changed – after some investigation I realised each time I import it is dividing the budgeted quantities by 8 – I presume this is because there are 8 hours in the day in the calendar.

Can anyone please advise how this can be avoided?

 

Thanks

Replies

Mike Testro
User offline. Last seen 36 weeks 3 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi David

P6 is a pig to operate - it may be that you are set to hours and not days or something like that.

In ASTA you can just copy / paste directly from excell.

Why not multply by 8 before importing.

Best regards

Mike Testro