change of WBS when Importing P3 to P6

3 replies [Last post]
James bid
User offline. Last seen 10 years 10 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Good Day Planners!

May I ask your help regarding my problem in importing because whenever I import a program from P3 to P6, The Project ID at P3 automatically included in WBS code at P6. here what was happened...
in P3
Project ID Project Description
CP00 Construction Project 00

WBS(sample only)
BCA Briton Construction and Partners

in P6 (after importing)
WBS (sample only)
CP00.BCA Briton Construction and Partners

All the "CP00" was added to all WBS Code of the Project..
May I know what was the problem.

Thank you

Chris





Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Chris

View Activities: You have the columns
- WBS; shows the complete hierarchy
- WBS Name; Shows the name of that WBS-node
- WBS Path; Shows the code without the upper nodes
For you WBS Name or -Code I assume then it will be shown with each activity.

Summary lines: Group & Sort: Group By WBS, unmark: Show ID Code

Regards
Dieter
James bid
User offline. Last seen 10 years 10 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Thanks Dieter!

May I know how to hide the WBS Code? or just say Show only WBS name.

Because what the problem is upon I imported the program with the project ID CP00 to P6 The WBS was turned to CP00.BCA instead of BCA only
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Chris

This is by design. The first level of the WBS is the project itself. If You’ll show the WBS, the complete path will be shown. Alternative: Just show WBS-Name.

Regards
Dieter