why does budget hrs change when increasing remaining

3 replies [Last post]
Donovan Govender
User offline. Last seen 10 years 36 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
why does budget hrs change when increasing remaining
and activity has not started

Replies

Rodel Marasigan
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Donovan,

Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query.

HTH,
Rodel
Mark Roberts
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 28 Jun 2007
Posts: 16
Groups: None
Donovan

On the projects screen go to the calculations tab, & check the "Link Budget & At Completion for not started activities." I imagine this is ticked...

Cheers
Mark
David Kelly
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Because your "duration type" has units per time unit fixed.