Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2007-10-30 18:46 Permalink RE: why does budget hrs change when increasing remaining Donovan, Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query. HTH, Rodel Member for 21 years Member for 21 years Submitted by David Kelly on Tue, 2007-10-30 04:48 Permalink RE: why does budget hrs change when increasing remaining Because your "duration type" has units per time unit fixed. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2007-10-30 18:46 Permalink RE: why does budget hrs change when increasing remaining Donovan, Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query. HTH, Rodel
Member for 21 years Member for 21 years Submitted by David Kelly on Tue, 2007-10-30 04:48 Permalink RE: why does budget hrs change when increasing remaining Because your "duration type" has units per time unit fixed.
Member for
19 yearsRE: why does budget hrs change when increasing remaining
Donovan,
Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query.
HTH,
Rodel
Member for
21 yearsRE: why does budget hrs change when increasing remaining
Because your "duration type" has units per time unit fixed.