when I import updated data I lose the WBS data, perhaps there should be no format when importing?

J
John Reeves 👤 Member for 13 years 2 months

when I import updated data I lose the WBS data, perhaps there should be no format when importing?  Does certain wbs info have to be in the export - what am I doing wrong.  Anytime I go a year without doing something I forget the associated "tricks".

R
Rodney Jones 👤 Member for 14 years 1 month

Hey John,

 

Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?

R
Rodney Jones 👤 Member for 14 years 1 month

Hey John,

 

Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?

R
Rodney Jones 👤 Member for 14 years 1 month

Hey John,

 

Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?

S
Santosh Bhat 👤 Member for 21 years 3 months

John,

WBS has to be imported, or else all activities are by default dropped into the very top level node.

Featured Partner

Top Posters

Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts
Manjeet Yadav
0 posts
Pan
0 posts
Tijo Kurian
11 posts
Zainab El-Beialy
3 posts