Resource Types When Importing from P3 to P3e

2 replies [Last post]
Kevin Donaghy
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 5 Jun 2003
Posts: 11
Hi,

When importing a project from P3 v3.1 to P3e v 4.1, how and what controls how v4.1 determines what type of resource it is.

I have imported a project, and some of the resources are now non-labour, and v4.1 will not allow me to change the resource type.

Any suggestions / advice.

Regards

Kevin

Replies

Kevin Donaghy
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 5 Jun 2003
Posts: 11
Hi Joao,

Thanks for that, but my unit of measure was Mhr (Man hours)and t (tonnes), I will try just using mh and ton and see what that does.

Cheers

Kevin
Joao Ribeiro
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
That is determined by PRMCONVERT.INI file. Please see page 463 of Administrator guide. In short: resources are converted to labour, non-labour or material according to rules set in that file, so changing the file changes the rules. Hope this will help you.