Milestone Activities with invalid relationships

2 replies [Last post]
Akhilesh Nadgauda
User offline. Last seen 14 years 10 weeks ago. Offline
Joined: 29 Jun 2010
Posts: 5
Groups: None
Hi Guys,

I performed the following steps on P6:

1. Export P6 schedule from Project A into excel.
2. Import activities and activity relationship from Project A excel spreadsheet into Project B.

Then, I ran a P6 schedule and was going through the log. I noticed that the log said "Milestone Activities with invalid relationships". These were the milestones that I had imported from another project.

Do you know why this error message showed up? The activity codes and relationships seems to look exactly like the old project.

Please help!!

Thanks.

Replies

Akhilesh Nadgauda
User offline. Last seen 14 years 10 weeks ago. Offline
Joined: 29 Jun 2010
Posts: 5
Groups: None
That makes sense, will check it out. Thanks!
Rodel Marasigan
User offline. Last seen 1 week 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Akhilesh,
Check the milestone if Start Milestone or Finish Milestone. If previous link is FS or FF to Finish Milestone it will create invalid relationship. By default P6 excel import Milestone as Start Milestone that produce this error.